2007 Street Reconstruction Program
2007 Street Resurfacing and Crack Seal Program
(This project is also referred to as the 2007 Motor Fuel Tax (MFT) Street Maintenance Program)Construction General Contractor: J.A. Johnson Paving
Note: The 2007 Street Resurfacing and Crack Seal Program is a separate project (completed under a separate contract) from the 2007 Street Reconstruction Program. The construction schedule of the project is estimated to be ongoing thru the months of July and August of 2007. For further detailed information please contact the Village of Itasca Public Works Department at (630) 773-2455.
Streets highlighted in red on the above location map:
The maintenance work on the below listed street locations #1 thru #3 includes: surface and base patching, minor curb and gutter spot repairs, cold milling, leveling binder, hot-mix asphalt surface course, and thermoplastic pavement markings.
| Street | Limits | |
|---|---|---|
| 1. | Theodore Lane | Walnut Avenue to N. Cherry Street |
| 2. | Theodore Lane | Cherry Street to Arlington Heights Road |
| 3. | Intersection of Bloomingdale Road and Lombard Road/Forest Avenue |
Streets highlighted in blue on the above location map:
The maintenance work on the below listed streets/locations #4 thru #8 includes crack sealing.
| Street | Limits | |
|---|---|---|
| 4. | Lombard Road | W. Bloomingdale Road to S. Oak Street |
| 5. | Arlington Heights Road | E. Division Street to Thorndale Avenue |
| 6. | E. Division Street | N. Walnut Street to Arlington Heights Road |
| 7. | S. Park Boulevard | Clover Ridge Lane to Thorndale Avenue |
| 8. | Arlingdale Subdivision | |
| Alexandra Court | Arlington Heights Road to Cul-de-sac | |
| N. Cherry Street | E. Bryn Mawr Avenue to Theodore Lane | |
| Cherry Circle | N. Cherry Street to Cul-de-sac | |
| Cherry Court | N. Cherry Street to Cul-de-sac | |
| N. Elm Street | E. Bryn Mawr Avenue to Walters Lane | |
| Elm Circle | N. Elm Street to Cul-de-sac | |
| Elm Court | N. Elm Street to Cul-de-sac | |
| Linden Street | E. Bryn Mawr Avenue to Walters Lane | |
| Linden Court East | Linden Street to Cul-de-sac | |
| Linden Circle East | Linden Street to Cul-de-sac | |
| Linden Court West | Linden Street to Cul-de-sac | |
| Linden Circle West | Linden Street to Cul-de-sac | |
| N. Maple Avenue | W. Bryn Mawr Avenue to Theodore Lane | |
| Theodore Lane | N. Maple Avenue to N. Walnut Street | |
| N. Walnut Street | W. Bryn Mawr Avenue to N. Maple Avenue | |
| Walters Lane | N. Maple Avenue to Arlington Heights Road |
Disclaimer: The information contained on this website is for the use of providing periodic updates and information on the Village’s annual street reconstruction/maintenance projects to citizens, officials and others. It is not an official record, reporting or decision-making chronicle of the project. This site is not updated on a daily basis. The construction schedule is subject to change due to weather, equipment breakdowns, or other unforeseen circumstances. The construction Contractor is a separate company from the Baxter & Woodman, Inc. Baxter & Woodman, Inc. is not responsible for the construction Contractor’s construction means, methods, techniques, sequences, or procedures, time of performance, compliance with the Laws and Regulations, or safety precautions and programs in connection with the Project. Please contact the Village of Itasca Public Works Department at: (630) 773-2455 to confirm the latest information on the project.